Construction progress details
The progress table comes directly from the latest site update.
| SL. No | Name of the work | Progress details |
|---|---|---|
| 1 | Foundation work | 100% completed |
| 2 | Basement work | 100% completed |
| 3 | Super Structure work | 100% completed (Tower-1, Tower-2, Tower-3) |
| 4 | Block Work | Tower-01: all 8 apartments (A1 to A8) 100% completed. Tower-02: all 55 apartments 100% completed. Tower-03: all 51 apartments 100% completed. |
| 5 | Electrical conduiting work | Overall apartments 100% completed. Common area 90% completed. |
| 6 | Door frame fitting work | Overall 100% completed |
| 7 | Sanitary & plumbing line work | Internal wiring 100% completed |
| 8 | Inside plastering work | Overall 100% |
| 9 | Electrical cable wiring work | 100% apartments completed |
| 10 | Wall tiles work | Tower-1: 100%, Tower-2: 100%, Tower-3: 98% complete |
| 11 | Common sanitary & plumbing line work | Overall 95% completed |
| 12 | Outside plastering work | Tower-1 completed. Tower-2: 100%, Tower-3: 100% |
| 13 | Floor tiles/Marble work | Tower-1: 100% completed, Tower-2: 100% completed, Tower-3: 95% completed |
| 14 | L.C.C work | Tower-1 completed, Tower-2: 100% completed, Tower-3: 100% completed |
| 15 | Grill & Railing work | Tower-1: 100% completed, Tower-2: 100% completed, Tower-3: 100% completed |
| 16 | Inside paint & polishing work | Tower-1: 1st and 2nd coat 100% complete. Tower-2: 1st coat 100% completed. Tower-3: 1st coat, 10 apartments completed. |
| 17 | Switch-Socket fitting work | Tower-1 completed. Tower-2: 100% completed. |
| 18 | Outside paint work | Tower-1: 1st coat completed. Tower-2: 100% completed. |
| 19 | Door shutter work | Tower-1 completed. Tower-2 completed. |
| 20 | Aluminum work | Tower-1: 100% completed, Tower-2: 100% completed, Tower-3: 90% completed |
| 21 | Tiles pointing & marble finishing work | Tower-1 wall: 100% completed. Tower-2: 95% completed. |
| 22 | Commode-Basin fitting & C.P fittings work | 100% |
| 23 | Lift/Generator/Substation/Solar work | 95% |
| 24 | Boundary wall/Ground floor development work | 95% completed (boundary wall 95%, plaster 95%) |
| 25 | Roof top finishing work | Tower-1 tile work: 100% completed. Tower-2: 95% completed. Tower-3: 95% completed. |
| 26 | Roof top gardening / G.F garden work | Not yet started |
| 27 | Landscape / logo work | 90% |